KSC SHUTTLE STATUS 1/3/94
KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
Friday, Nov. 12, 1993
KSC Contact: Lisa Malone
MISSION: STS-61 -- HUBBLE SPACE TELESCOPE SERVICING
VEHICLE: Endeavour/OV-105 ORBITAL ALTITUDE: 356 miles
LOCATION: Pad 39-A INCLINATION: 28 degrees
TARGET LAUNCH DATE: December 1 CREW SIZE: 7
LAUNCH TIME: 4:57 a.m. EST LAUNCH WINDOW: 1 hour/11 min.
LANDING LOCATION: KSC
MISSION DURATION: 10 days/22 hours/36 min.
EXPECTED LANDING DATE/TIME: Dec. 12 / 3:33 a.m. EST
IN WORK TODAY:
* Helium signature leak test of the main engine fuel systems
* Pad B payload changeout room cleaning and inspections
* Preparations to transfer the vehicle to pad B
* Preparations to replace auxiliary power unit controller 2
WORK SCHEDULED:
* Move vehicle to pad B with first motion at noon Monday
* Replacement of protective covers on HST payloads
* Payloads to be transported to pad B at midnight on Monday
* Install payloads in orbiter next Friday
* Flight Readiness Review on Nov. 17
WORK COMPLETED:
* Successfully completed inspections of the three main engine high pressure
fuel turbopumps. No discrepancies were found.
* Loaded hypergolic propellants onto orbiter
MISSION: STS-60 -- WAKE SHIELD FACILITY AND SPACEHAB 2
VEHICLE: Discovery/OV-103 ORBITAL ALTITUDE: 218 miles
LOCATION: OPF bay 3 INCLINATION: 57.00 degrees
TARGET LAUNCH PERIOD: January CREW SIZE: 6
LAUNCH WINDOW: 3 hours/51 minutes LANDING LOCATION: KSC
MISSION DURATION: 8 days/5 hours
IN WORK TODAY:
* Tests of orbiter payload interfaces
* Preparations to install the SPACEHAB payload
* Transfer SPACEHAB to OPF
* Servicing the orbiter with ammonia
* Stacking right-hand solid rocket boosters in Vehicle
Assembly Building high bay 3
WORK SCHEDULED:
* Electrical verifications of the forward reaction control system
* Install SPACEHAB in orbiter's payload bay Monday
* Install three main engines next week
WORK COMPLETED:
* Installed forward reaction control system
* Interface Verification Test of Wake Shield Facility
* Flight control aerosurface checkouts
MISSION: STS-58 -- SPACELAB LIFE SCIENCES -2
VEHICLE: Columbia/OV-102 LOCATION: OPF Bay 2
LAUNCH DATE/TIME: October 18 / 10:53 a.m. EDT
LANDING DATE/TIME: November 1 / 10:06 a.m. EST at Edwards AFB
IN WORK TODAY:
* Remove tail cone
* Install strongbacks on payload bay doors
* Open payload bay doors
* Post-flight inspections
WORK SCHEDULED:
* Remove Spacelab Life Sciences payload next week
# # # # #
---
■ Via FTL BBS (404-292-8761) and NASA Spacelink (205-895-0028)