  2. KSC SHUTTLE STATUS 1/3/94 
  3.  
  4. KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
  5. Friday, Nov. 12, 1993
  6. KSC Contact: Lisa Malone   
  7.  
  8. MISSION: STS-61 -- HUBBLE SPACE TELESCOPE SERVICING 
  9.          
  10. VEHICLE: Endeavour/OV-105       ORBITAL ALTITUDE: 356 miles
  11. LOCATION: Pad 39-A                 INCLINATION: 28 degrees
  12. TARGET LAUNCH DATE: December 1     CREW SIZE: 7
  13. LAUNCH TIME: 4:57 a.m. EST         LAUNCH WINDOW: 1 hour/11 min.
  14. LANDING LOCATION: KSC
  15. MISSION DURATION: 10 days/22 hours/36 min.
  16. EXPECTED LANDING DATE/TIME: Dec. 12 / 3:33 a.m. EST
  17.  
  18. IN WORK TODAY:
  19. *  Helium signature leak test of the main engine fuel systems
  20. *  Pad B payload changeout room cleaning and inspections
  21. *  Preparations to transfer the vehicle to pad B
  22. *  Preparations to replace auxiliary power unit controller 2
  23.  
  24. WORK SCHEDULED:
  25. *  Move vehicle to pad B with first motion at noon Monday
  26. *  Replacement of protective covers on HST payloads
  27. *  Payloads to be transported to pad B at midnight on Monday 
  28. *  Install payloads in orbiter next Friday
  29. *  Flight Readiness Review on Nov. 17
  30.  
  31. WORK COMPLETED:
  32. *  Successfully completed inspections of the three main engine high pressure
  33.    fuel turbopumps. No discrepancies were found. 
  34. *  Loaded hypergolic propellants onto orbiter    
  35.  
  36. MISSION: STS-60 -- WAKE SHIELD FACILITY AND SPACEHAB 2
  37.  
  38. VEHICLE: Discovery/OV-103          ORBITAL ALTITUDE: 218 miles
  39. LOCATION: OPF bay 3                INCLINATION: 57.00 degrees
  40. TARGET LAUNCH PERIOD: January       CREW SIZE: 6
  41. LAUNCH WINDOW: 3 hours/51 minutes  LANDING LOCATION: KSC
  42. MISSION DURATION: 8 days/5 hours
  43.  
  44. IN WORK TODAY:
  45. *  Tests of orbiter payload interfaces 
  46. *  Preparations to install the SPACEHAB payload 
  47. *  Transfer SPACEHAB to OPF 
  48. *  Servicing the orbiter with ammonia
  49. *  Stacking right-hand solid rocket boosters in Vehicle 
  50.    Assembly Building high bay 3
  51.  
  52. WORK SCHEDULED:
  53. *  Electrical verifications of the forward reaction control system
  54. *  Install SPACEHAB in orbiter's payload bay Monday
  55. *  Install three main engines next week
  56.  
  57. WORK COMPLETED:
  58. *  Installed forward reaction control system 
  59. *  Interface Verification Test of Wake Shield Facility
  60. *  Flight control aerosurface checkouts
  61.  
  62. MISSION: STS-58 -- SPACELAB LIFE SCIENCES -2
  63.  
  64. VEHICLE: Columbia/OV-102             LOCATION: OPF Bay 2
  65. LAUNCH DATE/TIME:  October 18 / 10:53 a.m. EDT
  66. LANDING DATE/TIME: November 1 / 10:06 a.m. EST at Edwards AFB
  67.  
  68. IN WORK TODAY:
  69. *  Remove tail cone
  70. *  Install strongbacks on payload bay doors 
  71. *  Open payload bay doors
  72. *  Post-flight inspections
  73.  
  74. WORK SCHEDULED:
  75. *  Remove Spacelab Life Sciences payload next week
  76.  
  77.  # # # # #